West Side Wastewater Treatment Facility

Water Distribution/Sewage
Jonesboro, AR

Construction of approximately 2,500 linear feet of 28 ft wide crushed stone roadway
with graded ditches and six reinforced concrete stormwater pipes with flared
end sections. Also included is construction of approximately 2,400 linear feet of
24-inch sewer force main, 560 linear feet of 6-inch sewer force main, 1,250 linear
feet of 8-inch water main, and 1,000 linear feet of 2-inch water service line. Sewer
force main and water main construction includes bore under existing concrete
effluent channel. Mass grading consists of filling the existing, drained, lagoons.
Mass grading also includes site preparation and fill for the future WWTF construction.